Where is your Money Going?

Drilling Costs
​
-
Drilling Permit - $2,000.00
-
Legal - $6,000.00
-
Lease Hold Cost - $12,000.00
-
Liability Insurance - $8,000.00
-
Site Damages - $5,000.00
-
Roads & Location - $10,000.00
-
Drilling (Vertical) (Turnkey @ $25/ft. x 4,600ft) - $115,000.00
-
Drilling Rig Day Rate (30hr @ $450/hr) - $13,500.00
-
Drilling Water - $8,000.00
-
Electric Log - $8,000.00
-
Mud Log - $12,500.00
-
Drilling “Mud” - $10,000.00
-
Drilling Supervision - $15,000.00
-
Miscellaneous - $10,000.00
-
Roustabout Crew - $5,000.00
-
Total Intangible Drilling Costs - $228,000.00
-
Total Tangible Drilling Costs - $12,000.00
Total Estimated Drilling Costs - $240,000.00
Completion Costs
Tangible Completion Costs
-
Production Tubing (2 7/8”)(4,600’@$5.00/ft) - $23,000.00
-
Production Casing (5 ½”)(4,600’@$8.00/ft) - $37,000.00
-
Production Wellhead/Flowlines/Valves/Fittings - $6,000.00
-
Production Equipment: (Oil/Water Storage Tanks/Separator)(Surface-Sub-SurfacePumps/Packer) - $94,000.00
-
Total Tangible Drilling Costs - $12,000.00
Total Tangible Completion Costs - $172,000.00
Intangible Completion Costs
-
Casing Crew - $10,000.00
-
Cement Production Casing - $18,000.00
-
Cased Hole Perforation/CCL/Acoustic Log - $8,000.00
-
Acid/Slick Water Frac - $20,000.00
-
Worckover Rig (5 Days @ $2,280.00/Day) - $11,500.00
-
Well Testing - $6,000.00
-
Location Clean Up - $3,000.00
-
Roustabout - $5,000.00
-
Miscellaneous - $10,000.00
Total Intangible Completion Costs - $91,500
Total Costs
Total Estimated Drilling Costs - $240,000.00
Total Estimated Completion Costs - $251,500.00
Total Well Tangible Completion Costs - $172,000.00
Total Well Intangible Completion Costs - $319,500.00
Total Year 1 IDC Tax Deduction - $319,500.00
Total to Drill and Complete 1 Well:
$491,500.00